In Design-Bid-Build, what must be finished before construction begins?

Prepare for the NCARB Project Management Exam. Use multiple choice questions, hints, and detailed explanations. Gain confidence and excel in your exam!

Multiple Choice

In Design-Bid-Build, what must be finished before construction begins?

Explanation:
In Design-Bid-Build, construction can begin only after the design work is finished and construction documents are issued. The design phase produces drawings and specifications that define the project scope, materials, and methods. Contractors bid based on those complete documents, and the chosen contractor builds to them. Without a finalized design, bids are unreliable, scopes are unclear, and change orders during construction would erode cost and schedule control. Permits and approvals are also sought against those finalized documents, so they must be in place before breaking ground. While site surveys, procurement planning, and scheduling are important, they do not by themselves unlock construction—the process hinges on having a complete design and corresponding construction documents.

In Design-Bid-Build, construction can begin only after the design work is finished and construction documents are issued. The design phase produces drawings and specifications that define the project scope, materials, and methods. Contractors bid based on those complete documents, and the chosen contractor builds to them. Without a finalized design, bids are unreliable, scopes are unclear, and change orders during construction would erode cost and schedule control. Permits and approvals are also sought against those finalized documents, so they must be in place before breaking ground. While site surveys, procurement planning, and scheduling are important, they do not by themselves unlock construction—the process hinges on having a complete design and corresponding construction documents.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy