Phase bid is used for fast-track construction where the construction contracts are bid on piecemeal.

Prepare for the NCARB Project Management Exam. Use multiple choice questions, hints, and detailed explanations. Gain confidence and excel in your exam!

Multiple Choice

Phase bid is used for fast-track construction where the construction contracts are bid on piecemeal.

Explanation:
Phase bidding is a procurement approach that enables fast-tracking by letting portions of the project be designed and bid separately as soon as enough design detail is available. By breaking the project into packages and awarding contracts piecemeal, construction can begin on early components while later design work continues, accelerating the overall schedule. This method isn’t limited to any particular project type and is specifically used to overlap design and construction. It does, however, require strong coordination across interfaces and careful contract management to handle potential change orders and integration issues.

Phase bidding is a procurement approach that enables fast-tracking by letting portions of the project be designed and bid separately as soon as enough design detail is available. By breaking the project into packages and awarding contracts piecemeal, construction can begin on early components while later design work continues, accelerating the overall schedule. This method isn’t limited to any particular project type and is specifically used to overlap design and construction. It does, however, require strong coordination across interfaces and careful contract management to handle potential change orders and integration issues.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy